overview
Demolition & Construction
In the sections below you can find information about the demolition and construction process, updates about current and upcoming works, the latest newsletter, and information about how to contact our neighbourhood liaison manager.
AUGUST 2024
Works Complete
- Steelwork complete to Level 7
- Blockwork complete to Basement 1 & 2
- South Bridge sections delivered
- Lobby landings to Level 10
- High level services continuing in Basement 2
- Toilet Fit out commenced in Basement 1
- Concrete to Level 3
SEPTEMBER 2024
Upcoming Works
- Concrete pour Level 4 & 5
- South Bridge to be lifted into position
- Steelwork and decking to Levels 7-9
- Lobby slabs to Level 12
- Heading works to commence
- Basement plant deliveries to commence
- High level MEP ongoing
- Racking columns at Ground floor to be cast
- Basinghall Street hoarding adaptions to incorporate vertical hoist for Façade install (disabled bay DB-S3 to be suspended)
construction
Phases
- Phase One: Demolition & enabling (Q1 2022 to Q3 2023)
- Phase Two: Substructure & core (Q2 2023 to Q2 2024)
- Phase Three: Superstructure (Q2 2024 to Q1 2025)
- Phase Four: Envelope (Q3 2024 to Q4 2024)
- Phase Five: Fit-out (Q4 2024 to Q1 2026)
- Phase Six: Commissioning & externals (Q1 2025 to Q1 2026)
Click on each phase image to expand the plan and use the arrows to scroll through phases.
read our
Latest News
For further information on upcoming works, please use these links to download our latest newsletters.
Issue 25 - Nov 2024
Issue 24 - Sept 2024
Issue 23 - Aug 2024
Issue 22 - June 2024
Issue 20 - Nov 2023
Issue 21 - Mar 2024
Issue 19 - Oct 2023
Issue 18 - Aug 2023
actively seeking to
Minimise Disruption
We’re committed to managing the impact of the construction works so that disruption to the local area is kept to a minimum.
Before construction work begins, a ‘Construction Management Plan’ for the site is agreed with the City of London Corporation. The plan outlines how our construction works will take place as well as what mitigations will be put in place to minimise the impact on the local community during the works. This includes site operating hours, noise and vibration mitigation measures, and traffic measurement.
The project has signed up to the Considerate Constructors Scheme, which is a not-for-profit independent organisation founded to raise standards in the construction industry. All constructors signed up to the scheme must make every effort to ensure their site teams care about the appearance of the site, respect the local community, protect the environment, secure everyone’s safety, and value their workforce.
Throughout the construction process we will also ensure that the local community has access to the latest information on the key works taking place through regular meetings and updates, so that you can get in touch with any questions or to raise any issues relating to the construction works.
Dedicated Construction Neighbourhood Liaison Manager
Keltbray has appointed a dedicated Construction Neighbourhood Liaison Manager to honour our commitment to minimise disruption for local residents, businesses and people who work and visit the area.
The Construction Neighbourhood Liaison Manager is working with all contractors on site, ensuring that neighbours are kept regularly updated and will respond promptly to any issues or questions that arise.
If you have any questions about these works or would like to speak with the Construction Neighbourhood Liaison Manager, please contact:
Lloyd Graham
E lloyd.graham@keltbray.com
T 07718 478 285
Knighton Estates Limited is a registered company in England and Wales at
33 Cavendish Square, London W1G 0PW.
Company no: 00379493
VAT no: 233 369 073